National Aquatic Centre

A dated source record for Spring Hill’s major public infrastructure project.

Location
Centenary Pool / Victoria Park, Spring Hill
Delivery authority
Games Independent Infrastructure and Coordination Authority (GIICA)
Evidence stage
Site preparation and initial works reported; venue overview retains a planning and approvals label.
Checked
24 September 2026

What is confirmed

GIICA’s 1 September announcement records the site handover and closure of Centenary Pool. Its later September notice identifies surveys, service work and a section of footpath work on Gregory Terrace.

What to watch

Check for revised work notices, pedestrian diversions, main works milestones and published community-access arrangements. Dates and access may change. An initial-works notice does not establish that the main venue is complete or open.

Source chronology

  • 1 September 2026: site handover announcement.
  • Mid-September 2026: works and pedestrian-access notice.
  • 24 September 2026: this record checked against those documents and the venue page.